Introduction
|
|
============
|
|
|
|
This document proposes some enhancements for numpy and scipy releases.
|
|
Successive numpy and scipy releases are too far apart from a time point of
|
|
view - some people who are in the numpy release team feel that it cannot
|
|
improve without a bit more formal release process. The main proposal is to
|
|
follow a time-based release, with expected dates for code freeze, beta and rc.
|
|
The goal is two folds: make release more predictable, and move the code forward.
|
|
|
|
Rationale
|
|
=========
|
|
|
|
Right now, the release process of numpy is relatively organic. When some
|
|
features are there, we may decide to make a new release. Because there is not
|
|
fixed schedule, people don't really know when new features and bug fixes will
|
|
go into a release. More significantly, having an expected release schedule
|
|
helps to *coordinate* efforts: at the beginning of a cycle, everybody can jump
|
|
in and put new code, even break things if needed. But after some point, only
|
|
bug fixes are accepted: this makes beta and RC releases much easier; calming
|
|
things down toward the release date helps focusing on bugs and regressions
|
|
|
|
Proposal
|
|
========
|
|
|
|
Time schedule
|
|
-------------
|
|
|
|
The proposed schedule is to release numpy every 9 weeks - the exact period can
|
|
be tweaked if it ends up not working as expected. There will be several stages
|
|
for the cycle:
|
|
|
|
* Development: anything can happen (by anything, we mean as currently
|
|
done). The focus is on new features, refactoring, etc...
|
|
|
|
* Beta: no new features. No bug fixing which requires heavy changes.
|
|
regression fixes which appear on supported platforms and were not
|
|
caught earlier.
|
|
|
|
* Polish/RC: only docstring changes and blocker regressions are allowed.
|
|
|
|
The schedule would be as follows:
|
|
|
|
+------+-----------------+-----------------+------------------+
|
|
| Week | 1.3.0 | 1.4.0 | Release time |
|
|
+======+=================+=================+==================+
|
|
| 1 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 2 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 3 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 4 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 5 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 6 | Development | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 7 | Beta | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 8 | Beta | | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 9 | Beta | | 1.3.0 released |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 10 | Polish | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 11 | Polish | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 12 | Polish | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 13 | Polish | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 14 | | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 15 | | Development | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 16 | | Beta | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 17 | | Beta | |
|
|
+------+-----------------+-----------------+------------------+
|
|
| 18 | | Beta | 1.4.0 released |
|
|
+------+-----------------+-----------------+------------------+
|
|
|
|
Each stage can be defined as follows:
|
|
|
|
+------------------+-------------+----------------+----------------+
|
|
| | Development | Beta | Polish |
|
|
+==================+=============+================+================+
|
|
| Python Frozen | | slushy | Y |
|
|
+------------------+-------------+----------------+----------------+
|
|
| Docstring Frozen | | slushy | thicker slush |
|
|
+------------------+-------------+----------------+----------------+
|
|
| C code Frozen | | thicker slush | thicker slush |
|
|
+------------------+-------------+----------------+----------------+
|
|
|
|
Terminology:
|
|
|
|
* slushy: you can change it if you beg the release team and it's really
|
|
important and you coordinate with docs/translations; no "big"
|
|
changes.
|
|
|
|
* thicker slush: you can change it if it's an open bug marked
|
|
showstopper for the Polish release, you beg the release team, the
|
|
change is very very small yet very very important, and you feel
|
|
extremely guilty about your transgressions.
|
|
|
|
The different frozen states are intended to be gradients. The exact meaning is
|
|
decided by the release manager: he has the last word on what's go in, what
|
|
doesn't. The proposed schedule means that there would be at most 12 weeks
|
|
between putting code into the source code repository and being released.
|
|
|
|
Release team
|
|
------------
|
|
|
|
For every release, there would be at least one release manager. We propose to
|
|
rotate the release manager: rotation means it is not always the same person
|
|
doing the dirty job, and it should also keep the release manager honest.
|
|
|
|
References
|
|
==========
|
|
|
|
* Proposed schedule for Gnome from Havoc Pennington (one of the core
|
|
GTK and Gnome manager):
|
|
http://mail.gnome.org/archives/gnome-hackers/2002-June/msg00041.html
|
|
The proposed schedule is heavily based on this email
|
|
|
|
* http://live.gnome.org/ReleasePlanning/Freezes
|